Published On:October 26 2020
Story Viewed 1494 Times

Law & order woes, approval delays: 441 infra projects see cost overruns.

Delays in land acquisition and green clearance, along with law and order problems, have made as many as 441 infrastructure projects, each worth at least Rs. 150 crore, run into cost overruns totalling more than Rs. 4.35 lakh crore.
As per a report by the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects costing Rs. 150 crore and above, there are 1,661 such central sector infrastructure projects of which nine are ahead of schedule and 206 are on schedule as on September 1, 2020.
The total original cost of implementation of the 1,661 projects was about Rs. 20.9 lakh crore but their anticipated completion cost is now expected to be about Rs. 25.26 lakh crore, which reflects cost overruns of over Rs. 4.35 lakh crore (20.81% of the original cost).
The expenditure incurred on these projects till August was Rs. 11.48 crore, or 45.47% of the total anticipated cost.
Law and order problems, delay in land acquisition and obtaining forest/environment clearances, lack of infrastructure support and linkages along with geological surprises, delay in tie-ups of project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, teething troubles before commissioning and contractual issues are the primary reasons for time overruns as reported by various project implementing agencies, according to the report.
“It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are underreported,” the ministry said.
While 539 projects are delayed, 211 projects reported both time and cost overrun. Of the 539 projects, the highest number of delayed projects pertains to railways followed by road transport and highways, and petroleum.
“However, the number of delayed projects decreases to 440 if the delay is calculated on the basis of the latest schedule of completion,” it said.
Of the total, 98 projects have reported additional delays from their date of completion reported in the previous month. Of these, 26 are mega projects costing at least Rs 1,000 crore.
For 907 projects, neither the year of commissioning nor the tentative gestation period has been reported.
The ministry said while the project authorities had been requested to regularly enter the list of milestones for each project to facilitate better monitoring, not all of them were reporting such details.
ET




OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Ruban Softwares